Project

Camú River Basin (Guaigüí Dam) Multiple Harnessing

Santiago de los Caballeros, Dominican Republic

  • Client: National Institute of Hydraulic Resources (INDRHI)
  • Date: February 2001 - June 2003
  • Contract: US$ 600,000.00
  • Constructor asociado: Statkraft Groner

Hydraulic, hydrologic, structural, geotechnical, environmental, topographic and electrical studies and designs, preparing documents and technical specifications of a rockfill dam with a 76 m high concrete screen and a 200 m crowning.

Also, excavation for intake works, supply and energy generation, machinery room at the foot of the dam (50 m upstream from the dump tunnel exit) and a 2.0 MW hydroelectric generation unit.

Services provided by the firm:
• Design of a rockfill dam with a 76 m high concrete screen and a 200 m crowning

• Design of deviated tunnel with a 200 m3/s capacity

• Design of dump thru a tunnel with unloading capacity of 730 m3/s

• Design of 2.0 MW hydroelectric central

• Design of access roads

• Technical specifications